Skip to main navigation.

Non-Residential Permanent Structure

Overhead Single-Phase Line Extension/New Construction

Non-Residential – Permanent Structure

Example: (Barn, Shop, etc…)

 

Requirements to receive permanent residence benefits are as follows

  • Structure may not be temporary or seasonal: structure must be permanent
  • Requires 5 year minimum contract of service

 

Benefits of Permanent Residence

  • HOTEC will collect 100% Aid to construction for all line to be installed
  • 100% of line Extension at $4.00/ft. (non-refundable Aid to Construction)

 

Costs to Customer

  • Meter loop/Meter can
  • 4/0 URD service wire $2.15/ft. (Cost is for wire only.  Installation is customers responsibility)
  • 350 URD service wire $3.00/ft. (Cost is for wire only.  Installation is customers responsibility)

 

Restrictions

  • All service must meet National Electric Code; HOTEC reserves the right to disallow any service not up to NEC or HOTEC specifications.
  • If customer decides to go with underground service it must be buried a minimum of 24”.
  • Trench and backfill will be inspected prior to permanent service.

 

General Information

  • All URD service is member installed
  • Service wire and metering installations may be purchased from other electrical merchants as long as they meet NEC specifications.
  • Prices for construction and wire will be recalculated periodically.